JHA assists Guangxi Yulin Fumian Airport have a successful flight test

JHA assists Guangxi Yulin Fumian Airport have a successful flight test

  • Categories:Company news
  • Author:
  • Origin:
  • Time of issue:2020-05-18
  • Views:0

(Summary description)At 16:28 on May 8, a Boeing 737-800 civil airliner belonging to China Southern Airlines landed smoothly at Fumian Airport in Yulin, Guangxi, successfully completing its test flight, marking another solid step towards the official opening of the airport to air traffic.

JHA assists Guangxi Yulin Fumian Airport have a successful flight test

(Summary description)At 16:28 on May 8, a Boeing 737-800 civil airliner belonging to China Southern Airlines landed smoothly at Fumian Airport in Yulin, Guangxi, successfully completing its test flight, marking another solid step towards the official opening of the airport to air traffic.

  • Categories:Company news
  • Author:
  • Origin:
  • Time of issue:2020-05-18
  • Views:0
Information

  JHA assists Guangxi Yulin Fumian Airport have a successful flight test  

      At 16:28 on May 8, a Boeing 737-800 civil airliner belonging to China Southern Airlines landed smoothly at Fumian Airport in Yulin, Guangxi, successfully completing its test flight, which represents another solid step towards the official opening of the airport to air traffic.

  As an important contractor of civil aviation professional projects such as visual aids to navigation lighting project, civil aviation air traffic control project and airport weak electricity project at Fumian Airport in Yulin, Guangxi, Beijing King Hangan Airport Engineering Co.

  Successful test flight at Fumian Airport in Yulin, Guangxi

  Yulin Fumian Airport is a major livelihood and transportation project in Yulin, and is of strategic importance in improving Yulin's transportation system and promoting Yulin's economic development. Construction of the airport started in November 2016 and has so far completed the completion of the flight area acceptance, school flight, test flight and flight area industry acceptance, and is expected to be officially opened to traffic in August 2020.

  Trust based value and records set within the area

       Yulin Fumian Airport is the first regional airport in China to be built in the EPC mode, and it is the first comprehensive project for JAC to enter the South Central region, which is an ice-breaking path to open up the South Central market. In this regard, King AirAsia attached great importance to the project, organized it carefully, planned it scientifically and deployed it thoroughly, set up the Yulin project department and entered the construction site in April 2019, went all out to promote the construction of various projects in an orderly manner, and successively constructed the airport visual aid lighting project, civil aviation air traffic control project, airport weak electricity project and other civil aviation professional projects.

  Under the circumstances of high incidence of thunderstorms, high construction terrain, tight construction schedule and heavy workload, all staff of Yulin Project Department always keep in mind the company's mission, play the company's fine tradition of daring to fight tough battles and being able to fight tough battles, adhere to the work style of "serious, meticulous and high standard", turn many "impossible 

      Only 4 months - from the start of the project to the completion of the acceptance of the project, it took only 4 months, creating a new record for the construction of domestic air traffic control projects.

  Only 20 days - from the airport school flight to the completion of the test flight, which made the airport command, construction unit and general contractor witness the "Beijing Air Safety Speed".

  Only 6 days - from the airport test flight to the one-time industry acceptance in only 6 days, which is a miracle in the industry.
 

  Be a "dreamer" of current time

  During the completion and acceptance of the flight area project in 2019, the navigation station, radar station, ATC building and tower were not fully equipped for installation. Under such circumstances, a group of people from the project department did not wait and did not rely on the project, cooperated with the renovation unit in a precise manner, inserted stitches and scrambled for time, organised personnel to concentrate on equipment installation and commissioning, and at the same time communicated closely with the equipment department of the company's organs to timely coordinate the relevant equipment manufacturers to enter the site for commissioning. With the concerted efforts, we finally completed the construction tasks for the completion and acceptance of the flight area in a quality and quantity manner.

  Successfully passed the completion inspection of the flight area project

     During the period of the new crown epidemic, the original schedule was interrupted, the project department organized the orderly entry of personnel under the condition of ensuring safety, and after the 14-day quarantine period, immediately put into on-site equipment commissioning and trial operation, effectively guaranteeing that all the equipment participating in the flight calibration, such as air traffic control and lighting, were in good condition, and laying a solid foundation for the school flight to proceed smoothly.

  During the school flight, the project department and the commissioning staff of the technical research department of the company's organs planned ahead, prepared various contingency plans, and made careful deployment of the personnel and vehicles participating in the school flight, and implemented every small work to the individual, and the professional and skilled commissioning technology and accurate school flight results were highly recognized and praised by the command department, the flight calibration centre of the Civil Aviation Administration, Guangxi Supervision Bureau, Guangxi Airport Group and the owner.

  Striving for time and building quality projects with heart

      According to the owner's control node of August 13 when the navigational information came into effect, the reporting of navigational information must be completed by May 21, which requires the project department to complete the acceptance of the flight area industry by May 20.

  In order to complete the task ahead of schedule, on April 27, after obtaining the construction permit for the security room of the airport terminal, the project department organized the relevant manufacturers of weak electricity, labour subcontracting teams and project personnel to work in a "day and night" "5+2" mode. "Three shifts were worked around the clock to seize every minute and second to seize the progress. The installation of each piece of equipment has added a touch of confidence to the project's timely delivery; every builder is sweating day and night. They had only one goal and belief: early completion and smooth delivery!

  Finally, on May 1, the project department completed the installation and commissioning of the equipment for the flight area perimeter video and remote aircraft monitoring, the flight area road crossing and the terminal security room.
 

  During the test flight, the leader of the airport command inspected and guided the work on site

  Successfully passed the industry acceptance of the airport flight area

  On May 5, the third party inspection unit completed the inspection and issued a qualified report; on May 6-7, the project successfully passed the completion acceptance; on May 7-8, it cooperated with the test flight work task led by the Central South Administration; on May 10, it successfully passed the project quality supervision report issued by the Civil Aviation Central South Quality Inspection Station; on May 14-15, it cooperated with Yulin Fumian Airport to complete the flight area industry acceptance and passed it in one go, laying a solid foundation for On 14-15 May, the airport completed the industry acceptance of the flight area and passed it in one go, laying a solid foundation for the next official opening of the airport.

  Yulin Evening News on Yulin Fumian Airport's Civil Aviation Professional System

  Conducting in-depth coverage

  Jinghang'An is deeply involved in the construction of this airport

  

Be brave in innovation and challenge yourself. Facing one technical problem and one time node, the people of Beijing Hangan have made one major breakthrough after another, refreshing the "Jing Hang' An speed" over and over again, practicing the business philosophy of "being an honest enterprise and creating high-quality projects" with practical actions and defending the brand of the enterprise. Honor. The Yulin Fumian Airport Construction Command, the construction unit and the general contractor have repeatedly sent letters of commendation to the project department in recognition of its outstanding contribution to the construction of the project, encouraging the people of Beijing Hang' An to make further efforts and create further successes!

  Never stop, perfection is the best. The project team will continue to build a sense of quality, create quality projects and serve our customers, and we are confident that in the upcoming acceptance of the terminal area industry, we will be able to deliver another good report and successfully complete all the subsequent construction tasks!

Scan the QR code to read on your phone

电话

Hotline :

010-81028028

地址

Address :

11th Floor, Block C, AVIC Plaza ,15 Rong Hua South Road, Yizhuang Economic Development Zone, Daxing District, Beijing

Links:
Follow us:
扫描此二维码关注我们